NEC ECC: Does Temporary Works apply under clause 20?

NEC3 ECC Main Option A.

The Contractor is responsible to construct only and the Employer provides the final design.

The Contractor has multiple temporary works design’s to complete as part of their work.

Does temporary works design need to follow 21.2 and have the temporary works design accepted by the Project Manager?

1 Like

Design of temporary works is covered by clause 23 as it is ‘Equipment’, so you only have to submit it for acceptance if the Project Manager instructs.