NEC ECC: Does an ambiguity in the BoQ permit the Contractor to notify a compensation event?

Excavation depths not identified in BoQ as method of measurement requires

NEC3 Option B provides for a CE in the case of an ambiguity in the BoQ, see clause 60.6