ReachBack
NEC 3 Option B Disputed Defects
NEC3 and NEC4 Contracts
Testing and Defects
dave_bates
26 July 2021 12:15
2
please see the response to the following by Neil Earnshaw
1 Like
show post in topic
Related topics
Topic
Replies
Views
Activity
ECC Option A contract - Defect
Testing and Defects
fastdraft
,
nec
,
proposed-instruction
2
1251
5 August 2021
NEC4 ECC: Defect before Completion of the whole of the works in an ECC Option A contract. The Client is responsible for designing the works
Secondary X, W and Y options
1
622
16 August 2019
NEC ECC: Cracks in paving construction ECC Option A Client Design - is this a defect?
Testing and Defects
4
2113
6 December 2020
NEC3 ECC: Process for correcting defects and accepting subcontractors
General
2
4345
6 December 2020
NEC ECC: A small area of new pavement construction has settled and is beginning to crack
General
4
3632
8 December 2020