Hi Peter,
Thanks for the response, its much appreciated.
Unfortunately the situation has still not been resolved with the Client and we are now having to change the welfare unit onsite to remove the office facilities for the Employers personnel. Naively with the welfare we acted on verbal instructions (and good faith) received at the the prestart meeting as the site establishment turnaround was rushed. We never received meeting minutes or the formal instruction and the PM is now denying the verbal instruction happened to reduce/cut costs. Regrettably the difference of opinions between myself and the Client PM on the matter has resulted in the PM adopting an attitude out with the principle of 10.1.
As noted in my original query we are currently working offline with work on the road network a few months away and I am being proactive in trying to resolve the issue around no Traffic Management items being contained within the BoQ.
The Client is taking the same stance with Equipment in relation to not including Traffic Management items in the BoQ. The Clients opinion is
“It is our view that Absent any items in the Price List for specific equipment, the costs attributed to any equipment is deemed to be included in the Prices/ Rates which have been tendered.”
Traffic Management is noted in the WI document as follows:
"The Contractor provides all necessary traffic management as shown below in Minor Civil Engineering Works – General Requirements.
Minor Civil Engineering Works - General Requirements
The Contractor is responsible for managing the activities involved in the execution of works. This will involve co-ordination with other bodies such as statutory undertakers and Roads Authorities.
*Adequate working space, warning signs, means of access and lighting must be provided by the Contractor. Precautions shall be taken against the possible presence of gas in the controller cabinet, at the tops of signal poles, cable draw pits and ducts. If any gas is suspected anywhere in the ducting system, then the local gas board shall be contacted immediately. *
*The Contractor shall have responsibility for liaison with statutory undertakers and the Roads Authority to ascertain the positions of all underground services that may be affected by the proposed installation of traffic signal equipment. *
*The Contractor shall ensure that all necessary measures are taken as required by any Statutory Undertaker and/or the Employer for the protection of its mains, pipes, cables or other apparatus during the progress of the works. The Contractor shall construct and provide as required any auxiliary works necessary for the prevention of damage and interruption to Statutory Undertakers and/or Employer services to their satisfaction. *
The Construction (Design and Management) Regulations 2015 (CDM) place duties on clients, planning supervisors, designers and contractors to plan, coordinate and manage Health and Safety throughout all stages of a construction project. In particular, the client has to ensure that any designer or contractor appointed is fully competent to execute the works and will allocate sufficient resources for Health and Safety. Each of the foregoing designated persons have specific duties under the Regulations. The Contractor shall be considered to be the Principal Contractor in terms of CDM."
There is multiple site locations and junctions contained within the Works and not enough or any information within the contract documents to adequately assess or price the works associated with this hence why we have from the early stages submitted an EW raising our concerns.
The Client is simply saying anything they have missed from the Price List is to be included in our other tendered rates which we think is unfair and not correct. We are trying to resolve this with them before it escalates and /or is referred to adjudication.
Any advice on the Traffic Management concerns would be much appreciated.
Thanks
Paul