NEC otion A:- We have a contract without X1 that has had significant delays. This has meant that materials and labour are now much more expensive than they would have been if the project had proceeded as originally planned and finished 2 years ago. Can I claim an increase to materials and labour as part of the delay claim compensation event? How about a change to the schedule of rates for the pricing of future events?
Any advise greatly appreciated.