In judging the physical conditions for assessing a compensation event, the Contractor is assumed to have taken into account what?
The Site Information,
Publicly available information referred to in the Site Information,
Information obtained from a visual inspection of the Site and,
Other information which an experienced contractor could reasonably be expected to have or to obtain (see Clause 60.2).