What are the three tests for assessing whether unexpected physical conditions constitute a compensation event?
The physical conditions are within the Site,
The physical conditions are not weather conditions and
An experienced contractor would have judged at the Contract Date that the conditions have such a small chance of occurring that it would have been unreasonable for him to have allowed for them (see Clause 60.1(12)).