If Equipment is owned by a parent company of the Contractor, is the cost of hire included in the SCC?

If Equipment is owned by a parent company of the Contractor, is the cost of hire included in the SCC?

1 Like

No. If the Equipment is owned by the Contractor’s parent company or the Contractor himself, it is not included in the Schedule of Cost Components.

Assuming that we are using NEC3 ECC Option C thenthis has to be a YES - SOCC Equipment 2. 22
Payments for Equipment which is not listed in the Contract Data but is