How long does the Contractor have to reply to a communication?

How long does the Contractor have to reply to a communication?

1 Like

The Contractor replies within the period for reply agreed in the Contract Data unless the contract states otherwise (see Clause 13.3). The Project Manager may extend the period for reply in accordance with Clause 13.5.