Each time the Contractor submits a programme to the Project Manager for acceptance, what provisions must he include?

Each time the Contractor submits a programme to the Project Manager for acceptance, what provisions must he include?

The Contractor shows on each programme he submits for acceptance provisions for:

	Float

	Time risk allowances,

	Health and safety requirements and,

	The procedures set out in the contract (see Clause 31.2).

Unless this is the first programme issued for acceptance it should also include the provisions within clause 32.1 to reflect progress and change. 31.2 and 32.1 act as useful checklists as to what the programme should show, but there may also be further requirements listed within the Works Information.