Does the tender programme become the Accepted Programme?

Does the tender programme become the Accepted Programme?

If the Contractor includes a programme at tender stage in part two of the Contract Data, and the tender is accepted without alterations, the Contractor’s tender programme will become the first Accepted Programme if it is authorised in part one of the Contract Data. If this is not the case, part one of the Contract Data will tell the Contractor within how many weeks of the contract award they would need to submit their first programme for acceptance.