Is the Contractor required to take out insurance cover?
1 Like
Yes. The Contractor provides the insurances stated in the Insurance Table (Clause 84.2) except any insurance which the Employer is to provide as stated in the Contract Data. The Contractor provides additional insurances as stated in the Contract Data (see Clause 84.1).