Does the Contractor have a duty to co-operate with Others?
1 Like
Yes. As stated in Clause 25.1, the Contractor must co-operate with Others in obtaining and providing information which they need in connection with the works. The Contractor also shares the Working Areas with Others as stated in the Works Information.