As a sub-contractor we have been instructed to issue an updated Clause 32 programme.
We have a number of access dates in the contract data which have not been made available to us and so this is a CE under 60.1.2.
We cannot get firm access dates to certain areas from the contractor so how do we deal with this within our clause 32 programme submission?