CE's Issued Under 60.1 or 61.1?

The class is split on this one. We have been receiving CI’s under clause14.3, but then corresponding CE’s issued under clause 61.1, i.e. In accordance with Cl61.1 this is a Compensation Event’. However there is a debate ongoing as to whether the CE notice should say ‘In accordance with 60.1(1), this is a Compensation Event’. Both sound plausible. For me, 61.1 is an obligation and 60.1 states what the CE is, so more siding to 60.1, Cheers.

I agree with you. When a CE occurs the Contractor is ‘obligated’ under 61.1 / 61.2 to notify the compensation event, which is one tick in the box, the second tick in the box is to notify the compensation event type i.e. change to Works Information / Scope 60.1 (1).