Can the Project Manager assess compensation events using the Shorter Schedule of Cost Components?

Can the Project Manager assess compensation events using the Shorter Schedule of Cost Components?

Yes. The Project Manager may make his own assessments using the Shorter Schedule of Cost Components (see Clause 63.15).