How is the Shorter Schedule of Cost Components used in Option D?

How is the Shorter Schedule of Cost Components used in Option D?

It can be used: to assess a compensation event even if the Project Manager and the Contractor are in agreement; or by the Project Manager when he is making his own assessments of a compensation event.