Can the Employer prevent a target being met?
No. If the Employer tries to prevent a target being met, he will be in breach of Clause 10.1 (acting in a spirit of mutual trust and co-operation). Achieving KPIs should be mutually beneficial, so the Employer should not try to prevent a target being met.