Can the Client add a Key Performance Indicator to the Schedule of Partners?
Yes. The Client may add a Key Performance Indicator and associated payment to the Schedule of Partners (see Clause X12.4(2)). However, the Client should consult with the other Partners before adding a KPI. The effect on subcontracted work should be noted; adding a KPI to work which is subcontracted can involve a change to the relevant KPI for the Subcontractor and/or Subcontract.