Can the Client delete a payment attached to a Key Performance Indicator and stated in the Schedule of Partners?

Can the Client delete a payment attached to a Key Performance Indicator and stated in the Schedule of Partners?

No. The Client may not delete or reduce a payment stated in the Schedule of Partners (see Clause X12.4(2)).