There is no particularly straightforward method. Delays can impact upon a contract in many and multifarious ways and attempting to assess the effects of such delays can be rather difficult.
Related topics
Topic | Replies | Views | Activity | |
---|---|---|---|---|
Contractors sometimes demand 'prelims' on the extension of time. How are these calculated? | 1 | 1255 | 5 February 2013 | |
If bank funding is delayed, is it legally permissible for an employer to delay payment? | 1 | 413 | 5 February 2013 | |
Construction law under the JCT | 1 | 649 | 10 April 2017 | |
Should time be considered 'of the essence' in construction contracts? | 1 | 454 | 5 February 2013 | |
With regard to construction contracts, what can be inferred by the term 'reasonable time'? | 1 | 435 | 4 February 2013 |