Are prices adjusted for inflation in Option D: Target Contract with Bill of Quantities?

Are prices adjusted for inflation in Option D: Target Contract with Bill of Quantities?

If Option X1: Price adjustment for inflation is used, then prices are adjusted for inflation. This option can only be used with main options A,B,C and D.