Are prices adjusted for inflation in Option A: Priced Contract with Activity Schedule?
If Option X1: Price adjustment for inflation is used, then prices are adjusted for inflation. This option can only be used with main options A,B,C and D.
Are prices adjusted for inflation in Option A: Priced Contract with Activity Schedule?
If Option X1: Price adjustment for inflation is used, then prices are adjusted for inflation. This option can only be used with main options A,B,C and D.