Are prices adjusted for inflation in Option C: Target Contract with Activity Schedule?

Are prices adjusted for inflation in Option C: Target Contract with Activity Schedule?

If Option X1: Price adjustment for inflation is used, then prices are adjusted for inflation. This option can only be used with main options A,B,C and D.