Ambiguity in Works Information

Nec 3, Option B Contract: There is an ambiguity in the Employers Work Information. The Works Information contradicts a “Z” clause amendment. Is it correct the Works Information is the higher precedent ? based on the requirement of Cl 20.1 “The Contractor provides the works in accordance with the Works Information”.

No. ‘Conditions’ of contract would have higher precedence than ‘terms’ in the Works Information.