|
NEC3 ECS - Delay Damages - recovering Contractors costs from Subcontractor
|
|
1
|
1318
|
13 January 2017
|
|
NEC3 ECC: What is the usual level of insurance where X18 is in the contract?
|
|
1
|
1607
|
1 November 2016
|
|
NEC3 ECC: Liability for defects
|
|
2
|
1227
|
9 October 2016
|
|
NEC3 Option Y(UK)3
|
|
1
|
1489
|
18 September 2016
|
|
NEC3 TSC Option A and X19 Secondary Option
|
|
2
|
3037
|
17 July 2016
|
|
X1 - Price Adjustment for Inflation - Can you offer advice on a cap on the index rates used?
|
|
1
|
961
|
24 June 2016
|
|
NEC3 ECC: Key date vs x7
|
|
1
|
1037
|
20 May 2016
|
|
X5 &7- Contractor cost incurred
|
|
1
|
560
|
20 May 2016
|
|
NEC3 ECC: KPI on secondary option X1
|
|
1
|
1275
|
19 May 2016
|
|
NEC3 ECC: X5 & 7 - Damages that Contractor would incur
|
|
1
|
812
|
18 May 2016
|
|
NEC3 ECC: Secondary Option X7 & x18.4 - Damages
|
|
1
|
3027
|
15 March 2016
|
|
NEC3 ECC: X18.4 Limitation of Liability
|
|
1
|
1415
|
26 February 2016
|
|
NEC3 ECC: X18 Contractor's liability
|
|
2
|
1834
|
26 February 2016
|
|
NEC3 ECC: Project does not fall into catagory for Housing Grants Act
|
|
1
|
843
|
4 December 2015
|
|
NEC3 ECC: Does Insurance Premium Tax and minimum wages constitute changes in the Law?
|
|
1
|
1350
|
27 November 2015
|
|
NEC3 ECS: X16 Retention bond as an alternative to retention?
|
|
1
|
1371
|
19 November 2015
|
|
NEC3 TSC: Can Service Manager instruct a Task Order under X19 and make own assessment?
|
|
1
|
1983
|
17 September 2015
|
|
NEC3 ECC: Use of secondary option X12 Partnering
|
|
1
|
6211
|
7 July 2015
|
|
NEC3 ECC: How is X6 dealt with if there is an instruction to reduce the scope of works?
|
|
1
|
1555
|
14 April 2015
|
|
NEC3 ECC: Who is obliged to notify a compensation event for an X2 change in law?
|
|
1
|
2578
|
2 March 2015
|
|
How do I allow for Price Adjustment for inflation X1 for contracts under a Framework Agreement
|
|
2
|
1786
|
23 February 2015
|
|
NEC3 ECC: What is the first contractual step to trigger adjudication?
|
|
1
|
801
|
9 February 2015
|
|
No timescale stated in X7 contract data part 1
|
|
2
|
922
|
12 January 2015
|
|
ECC Option C - Retention Arrangements
|
|
3
|
2444
|
21 July 2014
|
|
Does the Adjudicator consider tender documentation or only post award matters
|
|
2
|
1491
|
10 April 2014
|
|
Do X5 Liquidated Damages or Delay Damages have VAT charged to them when applied under NEC3?
|
|
1
|
1982
|
24 July 2013
|
|
Can X20 under NEC3 ECC be used to deduct money for poor performance under a KPI?
|
|
1
|
4261
|
14 June 2013
|
|
How long does a Contractor have to response to a request for a Task Order quotation under TSC X19?
|
|
1
|
920
|
8 April 2013
|
|
If the Contractor suspends performance, is it a compensation event?
|
|
1
|
728
|
14 November 2012
|
|
Can the Contractor suspend performance under Option Y(UK)2?
|
|
1
|
839
|
14 November 2012
|