NEC3 ECC: KPI on secondary option X1

X1 - Inflation each month is applied to People, Equipment, Plant, Subcontractors and T+S, however it excludes Fee.

What about KPI’s? would the inflation be added to KPI’s paid during the contract?

This is under an ECC Option C

1 Like

The short answer is probably not.

The slightly longer answer is it would depend on how the KPI is described and whether there is an index referenced under X1 which links to that description.

For a longer answer, I would need to see the words in the contract.