|
What is the main benefit of the compilation of data and supporting evidence?
|
|
1
|
463
|
18 January 2013
|
|
Why is it good practice to set out claims in the format that they may eventually be presented in a dispute resolution forum, such as adjudication or arbitration?
|
|
1
|
658
|
18 January 2013
|
|
What must be ensured when a commercial settlement is advantageous to both the subcontractor and main contractor?
|
|
1
|
612
|
18 January 2013
|
|
Why do cost value reconciliation systems need to be checked regularly and prudently?
|
|
1
|
565
|
18 January 2013
|
|
What are cost value reconciliation systems?
|
|
1
|
616
|
18 January 2013
|
|
What is the procedure if subcontractors are employed and their work is subject to disruption or delay?
|
|
1
|
563
|
18 January 2013
|
|
Do most claims arise before, after or during the event?
|
|
1
|
485
|
18 January 2013
|
|
What mistake is commonly made in court cases with regards to the burden of proof?
|
|
1
|
488
|
18 January 2013
|
|
How does the burden of proof operate in English law?
|
|
1
|
478
|
18 January 2013
|
|
What is meant by the 'burden of proof'?
|
|
1
|
494
|
18 January 2013
|
|
What is the best way of avoiding submitting a claim that does not have contractual foundation?
|
|
1
|
405
|
18 January 2013
|
|
What are the most important factors with regards to the success of a claim?
|
|
1
|
490
|
18 January 2013
|
|
Is it always possible to pre-estimate loss related to liquidated damages?
|
|
1
|
539
|
18 January 2013
|
|
Are there are costs that liquidated damages does not apply to?
|
|
1
|
484
|
18 January 2013
|
|
What conditions must be satisfied in order for a court to consider that damages constitute a penalty?
|
|
1
|
673
|
18 January 2013
|
|
Under what circumstances will the courts intervene in a liquidated damages claim?
|
|
1
|
439
|
18 January 2013
|
|
What legal principle governs liquidated damages claims?
|
|
1
|
1119
|
18 January 2013
|
|
What is the intention of a liquidated damages clause?
|
|
1
|
741
|
18 January 2013
|
|
What are 'liquidated damages'?
|
|
1
|
475
|
18 January 2013
|
|
With regard to un-liquidated damages, is claiming for them a simple process?
|
|
1
|
527
|
18 January 2013
|
|
What are 'un-liquidated damages'?
|
|
1
|
574
|
18 January 2013
|
|
With regards to development and engineering projects, where does the greatest risk lie?
|
|
1
|
576
|
18 January 2013
|
|
What are 'co-lateral warranties'?
|
|
1
|
1145
|
18 January 2013
|
|
What problems can arise in relation to claims for latent defects?
|
|
1
|
622
|
18 January 2013
|
|
What are latent defects?
|
|
1
|
539
|
18 January 2013
|
|
What is the procedure when aspects of a completed project do not meet the standards set out in the contract but are not rejected due to circumstances surrounding the work?
|
|
1
|
446
|
18 January 2013
|
|
What legislation deals with the rectification period?
|
|
1
|
514
|
18 January 2013
|
|
With regards to the rectification period, what occurs if the contractor is in breach of contract?
|
|
1
|
542
|
18 January 2013
|
|
What is the intention of the rectification period?
|
|
1
|
609
|
18 January 2013
|
|
What is the usual procedure if a contractor delivers a building in which there are defects?
|
|
1
|
530
|
18 January 2013
|