Yes. The disadvantage of these provisions is that an employer may find themself in a situation where failure to complete on time losses them significant funds if, for example they are unable to let a building on a date promised to a tenant. This will result in a considerable one off loss that liquidated damages cannot compensate for.
Related topics
Topic | Replies | Views | Activity | |
---|---|---|---|---|
What are 'liquidated damages'? | 1 | 475 | 18 January 2013 | |
If an employer suffers no loss, is it still legally permissible to deduct liquidated damages? | 1 | 537 | 5 February 2013 | |
What are delay damages? | 1 | 770 | 16 October 2012 | |
Under JCT Standard Building Contract 2009, in a case in which practical completion is achieved with a list of defects attached, is it legally permissible for an employer to deduct liquidated damages until termination, if this is delayed due to insolvency? | 1 | 510 | 5 February 2013 | |
If possession of the Works has been completed, it is still legally permissible for an employer to claim liquidated damages? | 1 | 473 | 5 February 2013 |