Why might the Project Manager not accept the Contractor’s design of an item of Equipment?

Why might the Project Manager not accept the Contractor’s design of an item of Equipment?

1 Like

Clause 23.1 states three reasons why the Project Manager might not accept the Contractor’s design of an item of Equipment. If the design prevents the Contractor from providing the works in accordance with: the Works Information; the Contractor’s design which the Project Manager previously accepted; or the applicable law the Project Manager will not accept the design.