When may a dispute about a quotation for a compensation event which is treated as having been accepted be referred to the Adjudicator?

When may a dispute about a quotation for a compensation event which is treated as having been accepted be referred to the Adjudicator?

Between two and four weeks after the Project Manager has notified the dispute to the Employer and the Contractor. This first notification must not be made more than four weeks after the quotation was treated as accepted (see Adjudication table W1.3).