When is the final date for payment under Option Y(UK)2?
The final date for payment is fourteen days after the date on which payment becomes due (or a different period of time if stated in the Contract Data) (see Clause Y2.2).
When is the final date for payment under Option Y(UK)2?
The final date for payment is fourteen days after the date on which payment becomes due (or a different period of time if stated in the Contract Data) (see Clause Y2.2).