What would be the implications of entering very low amounts against the deductibles in the Contract Data?

What would be the implications of entering very low amounts against the deductibles in the Contract Data?

1 Like

Entering very low amounts or ‘nil’ against the deductibles (excess) will increase the insurance premiums. This is not in the best interests of the Employer.