What are the four possible categories of reply by the Project Manager to the Contractor’s quotation for dealing with a compensation event?

What are the four possible categories of reply by the Project Manager to the Contractor’s quotation for dealing with a compensation event?

1 Like

The Project Manager’s reply is either:

	an instruction to submit a revised quotation,

	an acceptance of a quotation,

	a notification that a proposed instruction will not be given or a proposed changed decision will not be made or

	a notification that he will be making his own decision (see clause 62.3).