What are the four possible categories of reply by the Project Manager to the Contractor’s quotation for dealing with a compensation event?
1 Like
The Project Manager’s reply is either:
an instruction to submit a revised quotation,
an acceptance of a quotation,
a notification that a proposed instruction will not be given or a proposed changed decision will not be made or
a notification that he will be making his own decision (see clause 62.3).