What should the Parties do if an Adjudicator has not been chosen by the start date?
If an Adjudicator has not been chosen, either Party may ask the Adjudicator nominating body to choose one (see Clause W1.2(3)).
What should the Parties do if an Adjudicator has not been chosen by the start date?
If an Adjudicator has not been chosen, either Party may ask the Adjudicator nominating body to choose one (see Clause W1.2(3)).