What should the Contractor do if he disagrees with an instruction given to him by the Project Manager or Supervisor?
1 Like
The Contractor’s recourse in this instance is to follow the chosen dispute resolution procedure chosen for the contract (Option W1 or Option W2). Even if he disagrees with an instruction given to him by the Project Manager or Supervisor, he should not refuse to obey the instruction. However, if the Works Information require the Contractor to do something which is illegal or impossible he should notify the Project Manager immediately (see Clause 18.1).