What should the Adjudicator do if the Parties submit contradictory facts or legal submissions?
If the Parties submit contradictory facts or legal submissions, the Adjudicator should summarise the arguments submitted to him, and then state his decision clearly, giving his reasons. These reasons should show how they led to the decision reached.