What must the Adjudicator do on receiving a Party’s notice of adjudication?
On receiving the notice of adjudication, the Adjudicator notifies the Parties either:
That he is able to decide the dispute in accordance with the contract or
That he is unable to decide the dispute and has resigned (see Clause W2.3(1)).