What is the main function of the Supervisor?
1 Like
The Supervisor’s main function is to ensure that work is carried out in accordance with the Works Information. This remit includes conducting tests of materials and workmanship as well as observing the Contractor’s tests. The Supervisor also indentifies and correctes Defects and later certifies remaining Defects when he issues the Defects Certificate.