What important dates should the Contractor show on each programme he submits for acceptance?

What important dates should the Contractor show on each programme he submits for acceptance?

The Contractor shows on each programme he submits for acceptance:

	the starting date, access dates, Key Dates and Completion Date,

	planned Completion,

	the order and timing of the operations which the Contractor plans to do in order to Provide the Works,

	the order and timing of the work of the Employer and Others as last agreed with them by the Contractor or, if not so agreed, as stated in the

	Works Information,

	the dates when the Contractor plans to meet each Condition stated for the Key Dates and to complete other work needed to allow the Employer and Others to do their work,

	the dates when, in order to Provide the Works in accordance with his programme, the Contractor will need

	 access to a part of the Site if later than its access date,

	acceptances,

	Plant and Materials and other things to be provided by the Employer and

	information from Others (see Clause 31.2)