What if precise dates are not available to enter in the interface schedule?

What if precise dates are not available to enter in the interface schedule?

1 Like

Approximate dates should be entered in the Works Information if precise dates are unavailable. If this is the case, soon after the starting date, the Contractor should agree more detailed programmes with the other parties and include this information in his own programme.