What happens when a Contractor’s quotation is treated as having been accepted by the Project Manager (i.e. when the Project Manager has not replied to the Contractor’s quotation)?
1 Like
A compensation event is implemented when a Contractor’s quotation is treated as having been accepted by the Project Manager (see Clause 65.1).