What happens if the Contractor is not given access to correct a Defect before the defects date?

What happens if the Contractor is not given access to correct a Defect before the defects date?

2 Likes

The Project Manager will judge the cost to the Contractor of correcting the Defect. This amount is paid by the Contractor (see Clause 45.2).