What happens if no entry is made for damages in the Contract Data and Option X7 is used?
If Option X7 is used and no entry or a ‘nil’ entry is made in the Contract Data, it is likely that the Employer will be unable to recover any damages if the Contractor fails to complete the works by the Completion Date.