What does the Project Manager do on receiving the Employer’s notification that he wishes to terminate?

What does the Project Manager do on receiving the Employer’s notification that he wishes to terminate?

1 Like

If the reason for terminating complies with the contract, he will issue a termination certificate to both Parties (see Clause 90.1). Termination procedures, as listed in the Termination Table, will then begin.