What does a KPI in the Schedule of Partners look like?
KPI: Number of days to complete each floor of the building framework
Target: 14 days
Measurement: Number of days between removal of falsework form the entire slab and from the slab below
Amount: Main contractor - £5,000 each floor; Formwork and concrete subcontractor - £2,000; structural designer - £750 each floor