Under the provisions of JCT Design and Build Contract, if an employer undergoes a site investigation report and the ground conditions are discovered to be different, who is liable for any extra expenditure incurred?

It is highly likely that the contractor will be able to claim against the employer should conditions significantly differ from those stipulated in the Employer’s Requirements.