The Employer has not provided materials, facilities and samples for tests and inspections as stated in the Works Information. Is this a compensation event?
1 Like
Yes. Clause 40.2 states that the Employer is required to provide materials, facilities and samples for tests as stated in the Works Information. Failure to do so results in a compensation event (see Clause 60.1(16)).