The Contractor needs to correct Defects in time to avoid delaying what?
1 Like
The Contractor needs to correct Defects in time to avoid delaying:
Completion (defined in Clause 11.2(2))
Sectional Completion of parts of the works if Option X5 is used.
meeting Key Dates (defined in Clause 11.2(9)).
Dates on the Accepted Programme for the Employer or Others to start work (Clause 25.1).