ReachBack
Should time be considered 'of the essence' in construction contracts?
JCT Contracts
JCT_Experts
5 February 2013 15:03
2
Generally not, unless it is specifically indicated to be so in the contractual terms.
Related topics
Topic
Replies
Views
Activity
With regard to construction contracts, what can be inferred by the term 'reasonable time'?
JCT Contracts
1
425
4 February 2013
In construction contracts, when the statement time is 'at large' is made, how does this occur?
JCT Contracts
1
431
5 February 2013
With regards to adjudication, are the various time periods of significance?
JCT Contracts
1
593
6 February 2013
Contractors sometimes demand 'prelims' on the extension of time. How are these calculated?
JCT Contracts
1
1242
5 February 2013
Should a contractor be aware of any time limit to remedy all defects at the end of the rectification period?
JCT Contracts
1
467
5 February 2013